Heike R2012-09 R67: Difference between revisions
From KIP Wiki
ā§¼kip-jumptonavigationā§½ā§¼kip-jumptosearchā§½
Line 28: | Line 28: | ||
** 09:00 : Status = T<sub>Dewar</sub>=155K, T<sub>Magn,l</sub>=152K, p<sub>VC</sub>=0.78mbar |
** 09:00 : Status = T<sub>Dewar</sub>=155K, T<sub>Magn,l</sub>=152K, p<sub>VC</sub>=0.78mbar |
||
** 10:00 : Start filling LHe |
** 10:00 : Start filling LHe |
||
** 15:10 : During 3rd can (after ~ 230 LHe in total) T<sub>RuOx</sub>=4.6K, p<sub>VC</sub>=3.3*10<sup>-3< |
** 15:10 : During 3rd can (after ~ 230 LHe in total): T<sub>RuOx</sub>=4.6K, p<sub>VC</sub>=3.3*10<sup>-3</sup>mbar |
||
** 15:58 : Pump VC |
|||
** 17:15 : He 100%, LHe in total '''~318l''' |
|||
** 18:45 : Stop pumping VC, p<sub>VC</sub>=4.7*10<sup>-5</sup>mbar |
|||
Revision as of 16:51, 17 September 2012
NEW
- Renewed and improved noise thermometer.
- The wiring for four Double-Channel-Squids is installed.
- Two more stainless steel Coax-Cables are installed with their own port at room-temperature. The are numbered #5 and #6. Up to now they end at the mixing chamber and are connected to each other.
- Two semi-rigid coax-cables were installed, too.
- Filter-boxes I, II and VI were improved by adding a second coil at the input (cryo-end) of the filter circuit. The coils were manufactured by WĆ¼rth Electronik, Part No. 744221, 2000H; 600mA; 0.42
TEST
- Testing new noise thermometer ...
TIME TABLE
- 30.08.2012: FIRST DAY - CLOSING, CLEANING & PRE-COOLING
- Closing cryostat and dewar. Cleaning/pumping lines.
- Exchange gas pVC~3mbar.
- 17:57 : Pre-cooling with 50l LN.
- 29.02.2012: SECOND DAY - LIQUID HELIUM
- 09:00 : Status = TDewar=155K, TMagn,l=152K, pVC=0.78mbar
- 10:00 : Start filling LHe
- 15:10 : During 3rd can (after ~ 230 LHe in total): TRuOx=4.6K, pVC=3.3*10-3mbar
- 15:58 : Pump VC
- 17:15 : He 100%, LHe in total ~318l
- 18:45 : Stop pumping VC, pVC=4.7*10-5mbar
- 01.03.2012: THIRD DAY - MIX IN
- 08:00 : Status = TDewar=78K, TMC,Si=80K, TMagn,u=81K, pVC=0.67mbar, connect 3rd can LHe
- 11:45 : TMC,Si=4K, start pumping vacuum vessel.
- 14:00 : Start condensing mix. T1=688mbar, T2=700mbar, T3=0mbar, p4=774mbar.
- 14:10 : 100% He-Level. Total consumption to reach this level: 428.2 litres (Five cans) .
- 16:20 : Close Heat-Switch (IPCS#4=1.5A, IH=0.5mA) @ TRuOx=700mK
- 17:20 : All mix is in, all pumps are running. ISTILL=3.0mA, TRuOx=90mK
- 02.03.2012: 4th DAY
- Testing FPD
- Connecting and Testing Pt-NMR
- 05.03.2012: 1st RAMP MAGNET
- Satus : Heat switch is closed.
- 12:40 : IM= 40 A, heat switch closed (1,5 A)
- 07.03.2012: 1st DEMAG
- 11:04 : Open HS, Ti= 19.6 mK (corresponding to Noise Thermometer), Bi= 3.96 T
- 19:06 : IM= 0.6 A, TNMR ~ 389 uK, NT was disturbed by additional noise contribution in the frequency spectrum.
- 08.03.2012: 2nd RAMP MAGNET
- 12:00 : IM= 40 A, heat switch closed (1,5 A)
- 14.03.2012: 2nd DEMAG
- ! Changed setup of PLM-4! See NMR-textbook page 23
- 11:04 : Open HS, Ti= 14.95 mK (corresponding to Noise Thermometer), Bi= 3.96 T
- 19:06 : IM= 0.1 A, TNT ~ 300uK ( caused by disturbances !!! ), TNMR ~ 85 K (!!!) in Curie Mode.
- 17.03.2012: 3rd RAMP MAGNET
- 13:05 : Closing heat switch.
- 13:38 : IM= 40 A, heat switch closed (1,5 A)
- 21.03.2012: 3rd DEMAG
- 10:43 : Open HS, Ti= 19.23 mK (corresponding to Noise Thermometer), TNMR= 19.045 mK, Bi= 3.96 T
- 10:59 : Start Demag: TNT= 17.80 mK
- 16:16 : Stop Noise-Thermometer read-out due to massive external distributions by additional noise (SQUID-Radio Moscow :) ).
- 18:50 : IM= 0.3 A, TNMR ~ 240 K in Curie Mode.
- 22.03.2012: MIX OUT
- Some rf-heating tests
- 14:30 : Start putting mix in tank 1 and 2.
- 18:00 : After using babypump :T1=688mbar, T2=700mbar, T3=0mbar, p4=1032mbar.
- ALL MIX IS DUMPED IN OUR TANKS