Heike R2012-02 R66: Difference between revisions
From KIP Wiki
ā§¼kip-jumptonavigationā§½ā§¼kip-jumptosearchā§½
Line 17: | Line 17: | ||
** 09:55 : Start filling LHe |
** 09:55 : Start filling LHe |
||
** 17:00 : Status after two cans ('''188.8l LHe''') =T<sub>MC,Si</sub>=80K, T<sub>Magn,u</sub>=50K, p<sub>VC</sub>=0.45mbar |
** 17:00 : Status after two cans ('''188.8l LHe''') =T<sub>MC,Si</sub>=80K, T<sub>Magn,u</sub>=50K, p<sub>VC</sub>=0.45mbar |
||
Line 27: | Line 26: | ||
** 16:20 : Close Heat-Switch (I<sub>PCS#4</sub>=1.5A, I<sub>H</sub>=0.5mA) @ T<sub>RuOx</sub>=700mK |
** 16:20 : Close Heat-Switch (I<sub>PCS#4</sub>=1.5A, I<sub>H</sub>=0.5mA) @ T<sub>RuOx</sub>=700mK |
||
** 17:20 : All mix in. I<sub>STILL</sub>=3.0mA, T<sub>RuOx</sub>=90mK |
** 17:20 : All mix in. I<sub>STILL</sub>=3.0mA, T<sub>RuOx</sub>=90mK |
||
* 01.03.2012: 4<sup>th</sup> DAY |
|||
** Testing FPD |
|||
** Connecting and Testing Pt-NMR |
Revision as of 11:06, 3 March 2012
NEW
- Pt-NMR read-out via two s.s. mini-coax. Signal Coil is connected with port #1 and #3.
Time Table
- 28.02.2012: FIRST DAY - CLOSING, CLEANING & PRECOOLING
- Closing cyrostat and dewar. Cleaning/pumping lines.
- Precooling with 50l LN.
- 29.02.2012: SECOND DAY - LIQUID HELIUM
- 07:50 : Status = TDewar=207K, TMC,Si=216K, TMagn,l=217K, pVC=2.15mbar
- 09:55 : Start filling LHe
- 17:00 : Status after two cans (188.8l LHe) =TMC,Si=80K, TMagn,u=50K, pVC=0.45mbar
- 01.03.2012: THIRD DAY
- 08:00 : Status = TDewar=78K, TMC,Si=80K, TMagn,u=81K, pVC=0.67mbar, connect 3rd can LHe
- 11:45 : TMC,Si=4K, start pumping vacuum vessel.
- 14:00 : Start condensing mix. T1=688mbar, T2=700mbar, T3=0mbar, p4=774mbar.
- 14:10 : 100% He-Level. Total consumption to reach this level: 428.2 litres (Five cans) .
- 16:20 : Close Heat-Switch (IPCS#4=1.5A, IH=0.5mA) @ TRuOx=700mK
- 17:20 : All mix in. ISTILL=3.0mA, TRuOx=90mK
- 01.03.2012: 4th DAY
- Testing FPD
- Connecting and Testing Pt-NMR